AMRUT Universe
AMRUT State Wise List of Grounded Projects
S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 24X7 Water Supply with SCADA for Panaji City Water Supply 83.97 Work Completed
2 Supply of treated effluent water from Tonca STP to Green Spaces and Institutions in Panaji City Water Supply 12.4 Work Completed
3 Upgradation of Sewerage Network for Panaji City Sewerage/Septage 107.76 Work Completed
4 Upgradation of Sewage Pumping Installation at Panaji City by Providing Installing and Commissioning Submersible Pump sets under AMRUT Scheme Sewerage/Septage 1.05 Work Completed
5 Development of Open Spaces Opposite Old IPHB COmplex at Altinho, Panaji, Goa Parks 0.74 Work Completed
6 Development of Altinho Steps near Portuguese Consulate and Church Square Urban Transport 1.36 Work Completed
7 Beautification and Upgradation of Azad Maidan square Parks 2.52 Work Completed
8 Development of the Walkway along Central Library Side of the Creek Urban Transport 2.28 Work Completed
9 Beautification of the Beach Front Prominade at Miramar Urban Transport 14.42 Work Completed
10 Rejuvenation of Clusters of Lanes of Althino Steps Urban Transport 3.88 Work Completed
11 Rejuvenation and Redevelopment of Internal Lanes of Mala Urban Transport 3.14 Work Completed
12 Rejuvenation of Mandovi River Promenade from Children's Park to Youth Hostel Miramar. Urban Transport 15.8 Work Completed
13 Refurbishment of Existing Pedestrian Bridge Linking Central Library and Creek Urban Transport 1.68 Work Completed
14 Providing, installing and commissioning of Vaccum sewer network along with house connection for low lying areas in panaji city, Goa with 5 years of operation and Maintainance Sewerage/Septage 8.72 Work Completed
15 Water Supply project for the Corporation of the City of Panaji under AMRUT - Providing, installing, testing and commissioning of 40 HP pumps set and allied works at Altinho tank premises Panaji Water Supply 0.26 Work Completed