| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Water Supply of Jangipur under AMRUT (Phase-II) | Water Supply | 81.12 | Work Completed |
| 2 | Development scheme at Netaji Subhas Park for 2017-18 under AMRUT | Parks | 0.35 | Work Completed |
| 3 | Development scheme at Sadarghat Park for 2017-18 under AMRUT | Parks | 0.5 | Work Completed |
| 4 | Development of Netaji Subhash Deep | Parks | 0.3 | Work Completed |