AMRUT Universe
AMRUT State Wise List of Grounded Projects
S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Extension of SPS Lal Mandir Rising Main and Allied works at Haridwar (Zone E 1) Sewerage/Septage 1.16 Work Completed
2 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone B & C (Middle Haridwar) Part 3 Water Supply 1.66 Work Completed
3 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone B & C (Middle Haridwar) Part 2 Water Supply 2.31 Work Completed
4 Prevention of water logging at New Haridwar and Bhopatwala area Drainage 2.43 Work Completed
5 Prevention of water logging at Kankhal, Ghas Mandi to Rajghat area Drainage 1.76 Work Completed
6 Remoulding & Extension of drains, Rising mains, Sump & Pumping plant - Incidence of water logging between Chandracharya & Shaheed Bhagat Singh chowk (Part II) Drainage 0.96 Work Completed
7 Abhishek Nagar and Indu Enclave Sewerage Scheme Sewerage/Septage 1.51 Work Completed
8 Sewerage system in partly area of Lodha Mandi and Tibdi in Haridwar Sewerage/Septage 0.66 Work Completed
9 Sewerage network & allied works (Rishikul to MPS Mayapur) Zone C (DPR C-1) Part-2 DPR Rs. 1.41 Cr. out of Rs. 3.89 Cr. EFC approved Sewerage/Septage 1.41 Work Completed
10 Laltara Pul park Parks 0.19 Work Completed
11 Meena Enclave Colony park Parks 0.1 Work Completed
12 Shivlok Colony park Parks 0.25 Work Completed
13 Mayur Vihar Colony park Parks 0.3 Work Completed
14 Sewerage network & allied works in (Rishikul to MPS Mayapur) Zone C in Haridwar (DPR C-1) Part -I of Rs. 2.48 Cr. out of Rs. 3.89 Cr. EFC approved Sewerage/Septage 2.48 Work Completed
15 Bharatmata Puram Colony park, Bhopatwala Parks 0.31 Work Completed
16 Himgiri Vihar Colony park, Krishna Nagar, Kankhal Parks 0.22 Work Completed
17 Shravan Nath Park, Mayapur Parks 0.23 Work Completed
18 Remoulding & Extension of drains, Rising mains, Sump & Pumping plant - Incidence of water logging between Chandracharya & Shaheed Bhagat Singh chowk Drainage 3 Work Completed
19 Sewer network & allied works in (Balmiki basti & Ghas mandi mohalla area) Zone F3 in Haridwar Sewerage/Septage 1.87 Work Completed
20 Sewerage network & allied works in (Chaklan & Ahbab Nagar) area in Zone-F2 in Haridwar Sewerage/Septage 3.92 Work Completed
21 Sewer network & allied works Zone F1(Babar colony, Pawan vihar, Trimurti nagar area) in Haridwar Sewerage/Septage 5.86 Work Completed
22 Sewer network & allied works Zone E2 (Tibdi, Chandracharya chowk area) Sewerage/Septage 1.76 Work Completed
23 Sewerage system in (Arya Nagar) area Zone E1 in Haridwar Sewerage/Septage 2.95 Work Completed
24 Sewer Network & allied works in Zone D3 (Gurubaksh Vihar, Sandesh vihar & Sarvapriya vihar) Sewerage/Septage 2.71 Work Completed
25 Sewerage network & allied works in (Mishra Garden, Alankar Vihar & Hanuman Gadhi) Area in Zone-D2 in Haridwar town. Sewerage/Septage 2.81 Work Completed
26 Sewerage network and allied works in (Kumar Gadha, Gyanlok & Sanyas Road) area in Zone-D1 in Haridwar town. Sewerage/Septage 2.64 Work Completed
27 Shaheed Jagdish Vats Park, Pul Jatwara, Jwalapur, Haridwar Parks 0.25 Work Completed
28 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone E1 & E2 (Jwalapur) Water Supply 6.66 Work Completed
29 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone D (Kankhal) Water Supply 5.97 Work Completed
30 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone B & C (Middle Haridwar) Water Supply 0.25 Work Completed
31 Laying & Jointing of pipeline & its appurtenant work in different streets of NNH Zone A (Bhopatwala) Water Supply 6.12 Work Completed
32 Govind Puri Park, Haridwar Parks 0.23 Work Completed