| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Augmentation & Rehabilitation of water supply system (balance works) at Abohar town under AMRUT (Left out by SPCPL) | Water Supply | 6.02 | Work Completed |
| 2 | Sewerage - Phase-II- South Side Zone-I | Sewerage/Septage | 14.95 | Work Completed |
| 3 | Sewerage-Phase-III (North Side-Zone-II) | Sewerage/Septage | 11.35 | Work Completed |
| 4 | Water Supply-Phase-III (South Side-Zone-I) | Water Supply | 1.28 | Work Completed |
| 5 | Water Supply-Phase-III (North Side-Zone-II) | Water Supply | 1.54 | Work Completed |
| 6 | Sewerage scheme | Sewerage/Septage | 92.1 | Contract Awarded |
| 7 | Rehabilitation of MPS | Sewerage/Septage | 1.21 | Work Completed |
| 8 | Abohar Water Supply- Phase-II | Water Supply | 9.1 | Work Completed |
| 9 | Lalalajpat Rai Children Friendly Park | Parks | 0.1 | Contract Awarded |
| 10 | subash nagar children friendly park | Parks | 0.15 | Contract Awarded |
| 11 | Development of green spaces and parks | Parks | 0.52 | Work Completed |
| 12 | Development of green spaces and parks SAAP-II | Parks | 0.24 | Contract Awarded |
| 13 | Water supply to achieve universal coverage | Water Supply | 27.06 | Contract Awarded |