| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Water Supply network in TP/ OG/ City area of remaining area of Anand | Water Supply | 10.33 | Work Completed |
| 2 | Green Space Work, Garden at T.P.4, 6 & 3 | Parks | 0.81 | Work Completed |
| 3 | Storm darin at Palika nagar to Kans, Gamdi vad, Lambhvel Treatment plant, TP 9 area including 100 ft/ 180 ft road, 80 ft road to prarthna vihar etc. | Drainage | 13.52 | Work Completed |
| 4 | Sewer Network Rising Main Gamdivad PS to STP | Sewerage/Septage | 11.01 | Work Completed |
| 5 | Lotiya Bhagol Garden | Parks | 0.52 | Work Completed |
| 6 | Storm drain from goya talav to kanod talav via panchal hall 1.8km box drain and pumping station | Drainage | 13.54 | Work Completed |
| 7 | Garden at Sardar Baug, Anand | Parks | 0.22 | Work Completed |
| 8 | 33.00 MLD STP at lambhvel, Anand | Sewerage/Septage | 27.8 | Work Completed |
| 9 | 13.5 MLD STP at TP-8, Anand | Sewerage/Septage | 12.11 | Work Completed |
| 10 | 6.5 MLD STP at Bakrol, Anand | Sewerage/Septage | 12.79 | Work Completed |