| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Development of RR peta and Rajiv Gandhi park - Phase II | Parks | 1.01 | Work Completed |
| 2 | Remodelling of UGD network, Construction of 10 MLD STP along with Sewerage Network for Town-I area and septage management for Town-II area - Phase II | Sewerage/Septage | 14.62 | Work Completed |
| 3 | Development of Krishna Canal Bund AMRUT 2016-17 | Parks | 0.97 | Work Completed |
| 4 | Providing UGD network and Construction of 5MLD STP for Zone -IV area and septage management for remaining area of the town | Sewerage/Septage | 15.59 | Work Completed |
| 5 | Providing Clear Water Pumping mains from Head water works to ELSR’s | Water Supply | 5.23 | Work Completed |
| 6 | Development of Postal Colony Municipal Park | Parks | 0.41 | Work Completed |
| 7 | Providing House Service Connections in Eluru Municipal Corporation under AMRUT Scheme | Water Supply | 2.29 | Work Completed |