S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Development of Bandar Kota park under AMRUT 2016-17 - Phase II Parks 1.01 Work Completed
2 Construction of storm water outfall drainage network - Phase II Drainage 7.93 Work Completed
3 Development of Bandar Kota park under AMRUT 2016-17 Parks 0.8 Work Completed
4 Construction of storm water outfall drainage network Drainage 11.09 Contract Awarded
5 5 MLD STP; including interceptor drains and septage management for entire city Sewerage/Septage 10.87 Contract Awarded
6 Construction of new filtration plant (22 MLD) providing household connections where pipe lines are laid Water Supply 17.69 Work Completed
7 Development of Sidimbhi Agraharam park Parks 0.32 Work Completed
8 Providing water supply House Service Connections, distribution lines and Pumping Mains wherever source is available in Machilipatnam Muncipality under AMRUT Scheme Water Supply 30.41 Work Completed