| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Development of Ayyalanadu Tank under AMRUT 2016-17 - Phase II | Parks | 1.01 | Work Completed |
| 2 | STP - 1 no 7 MLD including interceptor drains - Phase II | Sewerage/Septage | 13.76 | Contract Awarded |
| 3 | Clear Water Transmission Main (3.10 KM), HSC's Phase II | Water Supply | 3.11 | Work Completed |
| 4 | Development of Ayyalanadu Tank under AMRUT 2016-17 | Parks | 0.86 | Work Completed |
| 5 | STP - 1 no 7 MLD including interceptor drains | Sewerage/Septage | 5.91 | Work Completed |
| 6 | Clear Water Transmission Main (3.10 KM), HSC's | Water Supply | 1.33 | Work Completed |