AMRUT Universe
AMRUT State Wise List of Grounded Projects
S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Const. of Green Space/ Park after covering the Nallah along state motor Garage ,W.No.16,New Plot, Jammu Parks 0.73 Work Completed
2 Upgradation of Drainage in Jammu Municipal Corporation including Pilot Project for Linear Drainage in Jammu City Drainage 13.23 Work Completed
3 Providing & Laying of Sewerage Network along Akhnoor Road from Shakti Nagar Nallah (Cremation ground) to ChanderBhaga Mohinder Nagar Sewerage/Septage 1.28 Contract Awarded
4 Providing & Laying Sewerage Network of left over areas under 5 Nallah with 3 No. IPSs & their allied works on left side of Tawi River Sewerage/Septage 11.55 Work Completed
5 Construction/Improvement of Deep Drain/Nallah From Dewan Modern Breweries Talab Tillo Road upto its Outfall in Nallah passing through Kabir Nagar and Santra Morh (Hazuri Bagh) Drainage 3.29 Work Completed
6 development of park after construction of R.C.C Nallah in EWS Colony, Lower Roop Nagar Hosing Colony, Jammu (Phase-II) by way of Civil, Electric and Mechanical works Parks 10.78 Work Completed
7 Development of park alongside of nallah, Muthi camp JDA Parks 0.78 Work Completed
8 Drainage networks of Digiana in Between Preet Nagar and Nai Basti. Drainage 4.36 Work Completed
9 Construction / Upgradation of Drinage Nallahs passing through Trikuta Nagar, Gandhi Nagar, Nanak Nagar and Shastri Nagar Drainage 8.63 Work Completed
10 Construction of deep drain from daily Excelsior Forest land Janipur up to Patoli Baba Mastram Ashram through Ram Vihar Shant Nagar Janipur Drainage 5.45 Work Completed
11 Improvement/ Construction of Drainage System from CM Residence to DPS School via Shahidi Chowk, Jammu Drainage 1.18 Work Completed
12 Construction of Rajiv Nagar Nallah from RD 0-3000m Drainage 7.07 Work Completed
13 Construction of Nallah and drainage network near Nidesh Apartments along Chatha Chowadi Nallah & Sainik Colony area including area near Heritage school, Sainik Colony. Drainage 18.12 Work Completed
14 Construction of Drainage Scheme at Christian Graveyard Nallah Drainage 1.07 Work Completed
15 Improvement/ Up-gradation of Rehari Nallah D/S Jewel Chowk to its outfall (Phase II) Drainage 3.27 Work Completed
16 Construction of Drainage Network adjoining Kamla Palace, Phase -2 Drainage 4.4 Work Completed
17 Construction /Upgradation of Drainage Scheme from Canal Road (Aggarwal Complex) Govt. Guest house upto its outfall Drainage 5.28 Work Completed
18 Construction of drainage at Peerkho Nallah Drainage 3.69 Work Completed
19 Development of Green space on both sides of different Nallahs (Damesh Nagar and Gangyal). Parks 3.97 Work Completed
20 Construction of Multi-tier Parking at Panjtirthi, Jammu Urban Transport 27.87 Work Completed
21 Intelligent Traffic System Urban Transport 14.25 Work Completed
22 Development of Pedestrian Walkway along River Tawi from Peerkho to PHE Station Urban Transport 4.24 Work Completed
23 Const. / Imp. of main Rehari Nallah on back side of GGM Science College,Jammu:Phase-1 Drainage 1.14 Work Completed
24 Const. of Drainage network in Swagat Vihar Deeli with its outfall in nallah at Deeli, Jammu Drainage 1.2 Work Completed
25 Drainage Scheme for const. of drainage network in ST Mohalla back side of FCI Godowns and JKAP lines Channi Rama, Jammu Drainage 3.69 Work Completed
26 Drainage Scheme for construction of deep drain along Tawi Canal in Extn. Trikuta Nagar Drainage 1.63 Work Completed
27 Drainage Scheme for const. of deep drain Sharika Vihar Drainage 2.83 Work Completed
28 Drainage Scheme for construction of deep drain at Sunder Nagar Drainage 3.08 Work Completed
29 Drainage Scheme for const. of deep drain Saraswati vihar Topsherkhania. Drainage 1.6 Work Completed
30 Drainage Scheme for const. of deep drain Vasant Vihar via Bharat Nagar (Kamla Palace, Phase -1) Drainage 1.6 Work Completed
31 Drainage Scheme for const. of deep drain Rajiv Basti/ Bikram Chowk Drainage 1.08 Work Completed
32 Sewerage Treatment of 5 nallahs b) Construction of sewerage network system by way of laying of sewers, construction of manhole for 5 nallahs on left side of River Tawi. Sewerage/Septage 22.6 Work Completed
33 Sewerage Treatment of 5 nallahs a) Design, const, installation, commissioning and testing of 4.00 MLD swerage treatment plant (STP) for 5 No nallahs falling on Left side of River Tawi. Sewerage/Septage 7.8 Work Completed
34 Purchase of Sewer / Jetting Machine Etc Sewerage/Septage 3.1 Work Completed
35 Design, Construction, erection and commissioning of 164 KLD Septage Treatment Plant at Baghwati-nagar Jammu Sewerage/Septage 4.37 Work Completed