| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Improvement of Water Supply to uncovered areas of Balasore -PKG-13 (AMRUT/OD/BALASORE/WS/18) | Water Supply | 25.42 | Work Completed |
| 2 | Development of Park in Balasore (Chandmari padia, Gudipada, Darjipokhari) -Package 1 (AMRUT/OD/BALASORE/PR/03) | Parks | 0.72 | Work Completed |
| 3 | Improvement of WS to Balasore -Zone 3 (ward no. 8,9,10,15,19, 21(P), including slums (AMRUT/OD/BALASORE/WS/08) | Water Supply | 15.64 | Work Completed |
| 4 | Improvement of WS to Balasore -Zone 2 (ward no. 17,18(P),26(P), 28,29,30 ), including slums (AMRUT/OD/BALASORE/WS/07) | Water Supply | 7.96 | Work Completed |
| 5 | Constuction of Parks in Balasore (AMRUT/OD/Balasore/PR/02) | Parks | 0.8 | Work Completed |
| 6 | Improvement of water supply to different Areas of Balasore Municipality (AMRUT/OD/BALASORE/WS/17) | Water Supply | 4.74 | Work Completed |
| 7 | Improvement of WS to Uncovered Poor Urban Areas (30 nos. Uncovered Poor Urban Areas) (AMRUT/OD/BALASORE/WS/16) | Water Supply | 7.42 | Work Completed |
| 8 | Improvement of WS to Balasore -New Z1 (AMRUT/OD/BALASORE/WS/06) | Water Supply | 14.33 | Work Completed |
| 9 | Septage Management & ID works for Balasore AMRUT/OD/BALASORE /SG/05 | Sewerage/Septage | 3.79 | Work Completed |
| 10 | Improvement of WS to Balasore -Rehabilitation P5 (AMRUT/OD/BALASORE/WS/05) | Water Supply | 4.07 | Work Completed |
| 11 | Improvement of WS to Balasore -Rehabilitation P4 (AMRUT/OD/BALASORE/WS/04) | Water Supply | 4.07 | Work Completed |
| 12 | Improvement of WS to Balasore -Rehabilitation P3 (AMRUT/OD/BALASORE/WS/03) | Water Supply | 4.04 | Work Completed |
| 13 | Improvement of WS to Balasore -Rehabilitation P2 (AMRUT/OD/BALASORE/WS/02) | Water Supply | 4.05 | Work Completed |