| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Sewerage System of Rourkela- Zone 3 (Sewer network of RKL West-Balance) (AMRUT/OD/ROURKELA/SG/08) | Sewerage/Septage | 20 | Work Completed |
| 2 | Devlopment of Park in Rourkela (Chend Colony MIG, Chend Colony Kalingavihar, Basanti colony-2) - Package 2 (AMRUT/OD/ROURKELA/PR/07) | Parks | 0.69 | Work Completed |
| 3 | Devlopment of Park in Rourkela (Koel Nagar-2, Chend Colony B block-2) - Package 1 (AMRUT/OD/ROURKELA/PR/06) | Parks | 1.01 | Work Completed |
| 4 | Improvement of WS to 51 nos.slum in sector area (AMRUT/OD/ROURKELA/WS/09) | Water Supply | 9.79 | Work Completed |
| 5 | Improvement of WS to 46 nos. Slum in railway area (Ward no. 22,38&40) (AMRUT/OD/ROURKELA/WS/08) | Water Supply | 9.85 | Work Completed |
| 6 | Improvement of Sewerage System of Rourkela (AMRUT/OD/Rourkela/SG/01) | Sewerage/Septage | 20 | Work Completed |
| 7 | Construction of Parks in Rourkela (AMRUT/OD/ROURKELA/PR/05) | Parks | 1.54 | Work Completed |
| 8 | Improvement of WS to Rourkela -New Z1 & including Improvement of WS-Rising mains from Bisra chowk to Koelnagar (AMRUT/OD/ROURKELA/WS/03) | Water Supply | 35.21 | Work Completed |
| 9 | Improvement of WS to Rourkela - Uncovered Poor Urban Areas (11 nos. / 115 nos. ) Ward no - 4, 5, 14,16, 19, 20, 21, 23 & 33. (AMRUT/OD/ROURKELA/WS/07) | Water Supply | 4.03 | Work Completed |
| 10 | Improvement of WS to Rourkela -New Z2 (AMRUT/OD/ROURKELA/WS/04) | Water Supply | 9.26 | Work Completed |
| 11 | Construction of Park in Rourkela near Chhendcolny in front of LCR /65 - AMRUT/OD/Rourkela/PR/02 | Parks | 0.31 | Work Completed |
| 12 | Septage Management & ID works for Rourkela AMRUT/OD/ROURKELA/SG/07 | Sewerage/Septage | 2.46 | Work Completed |
| 13 | Improvement of WS to Rourkela - Headworks P1 (AMRUT/OD/ROURKELA/WS/06) | Water Supply | 1.57 | Work Completed |
| 14 | Improvement of WS to Rourkela -New Z3, (AMRUT/OD/ROURKELA/WS/05), ( Ward Covered: 36) | Water Supply | 7.2 | Work Completed |
| 15 | Improvement of WS to Rourkela -Rehabilitation P2 (AMRUT/OD/ROURKELA/WS/02) | Water Supply | 1.6 | Work Completed |
| 16 | Improvement of WS to Rourkela -Rehabilitation P1 (AMRUT/OD/ROURKELA/WS/01) | Water Supply | 10.02 | Work Completed |