AMRUT Universe
AMRUT State Wise List of Grounded Projects
S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Bhilai Water Supply Scheme (Deposit Work to CSEB) Part-2 Water Supply 1.13 Work Completed
2 Bhilai Water Supply Scheme (Deposit Work to CSEB) Part-1 Water Supply 0.22 Work Completed
3 Procurement of Suction cum Jetting machine (9000 Liters) 3 nos (Part-2) Sewerage/Septage 0.07 Work Completed
4 Procurement of Suction cum Jetting Machine (9000 litres) 03 nos (Part-1) Sewerage/Septage 1.27 Work Completed
5 Bhilai Water Supply Scheme (Deposit Work to NH) Water Supply 0.52 Work Completed
6 Bhilai Water Supply Scheme (Deposit Work to CSEB-Transformer) Part - 3 Water Supply 0.09 Work Completed
7 Bhilai Water Supply Scheme (Deposit Work to CSEB-Transformer) Part - 2 Water Supply 0.23 Work Completed
8 Bhilai Water Supply Scheme (Deposit Work to CSEB-Transformer) Part - 1 Water Supply 0.07 Work Completed
9 Bhilai Water Supply Scheme (Deposit Work to CSEB) Water Supply 1.2 Work Completed
10 Contruction of Bal Udyan Garden at Vaishali Nagar, ward-15 (Solar works) Parks 0.03 Work Completed
11 Contruction of Bal Udyan Garden at Vaishali Nagar, ward-15 (Playing Equipment) Parks 0.01 Work Completed
12 Contruction of Bal Udyan Garden at Vaishali Nagar, ward-15 (civil work) Parks 0.05 Work Completed
13 Construction of Garden at Trikona, Priyadarshini Parishar East, Ward-03 Parks 0.06 Work Completed
14 Development of Garden at Ward No. 60 - Shakti Vihar (Playing Equipment) Parks 0.01 Work Completed
15 Development of Garden at Ward No. 60 - Shakti Vihar (Electrification) Parks 0.01 Work Completed
16 Development of Garden at Ward No. 16 - Kurud (Playing Equipment) Parks 0.02 Work Completed
17 Contruction of Garden at Kurud, Ward-16 (Solar works) Parks 0.02 Work Completed
18 Development of Garden at Ward No. 01 - Khamaria (Playing Equipment) Parks 0.04 Work Completed
19 Development of Garden at Ward No. 01 - Khamaria (Electrification) Parks 0.04 Work Completed
20 DEVELOPMENT OF GARDEN AT WARD NO 28 - BAPUNAGAR (Playing Equipment) Parks 0.07 Work Completed
21 DEVELOPMENT OF GARDEN AT WARD NO 28 - BAPUNAGAR (Electrification) Parks 0.09 Work Completed
22 DEVELOPMENT OF GARDEN AT WARD NO 28 - BAPUNAGAR GARDEN (Civil Work) Part -3 Parks 0.18 Work Completed
23 DEVELOPMENT OF GARDEN AT WARD NO 28 - BAPUNAGAR GARDEN (Civil Work) Part -2 Parks 0.06 Work Completed
24 DEVELOPMENT OF GARDEN AT WARD NO 28 - BAPUNAGAR GARDEN (Civil Work) Part -1 Parks 0.16 Work Completed
25 Bhilai Water Supply Scheme Phase II (Construction of WTP) Water Supply 16.8 Work Completed
26 Bhilai Water Supply Scheme Phase II - Construction of Distribution Part-3 Water Supply 9.69 Work Completed
27 Bhilai Water Supply Scheme Phase II - Construction of Distribution Part - 2 Water Supply 17.22 Work Completed
28 DEVELOPMENT OF GARDEN AT WARD NO 70 - HUDCO GARDEN (Electrification) Parks 0.1 Work Completed
29 DEVELOPMENT OF GARDEN AT WARD NO 70 - HUDCO GARDEN (Playing Equipment) Parks 0.06 Work Completed
30 DEVELOPMENT OF GARDEN AT WARD NO 70 - HUDCO GARDEN (Civil Work) Parks 0.33 Work Completed
31 Water Supply Scheme Bhilai Phase II- Construction of OHSR at Kurud & Khamaria Water Supply 5.84 Work Completed
32 Procurement of Septage Management Equipments (Tractors 02 nos) Sewerage/Septage 0.1 Work Completed
33 Procurement of Septage Management Equipments (Vaccum Emptier 3000 litres) 02 nos Sewerage/Septage 0.14 Work Completed
34 Contruction of Tata Line Garden solar works at Shyam Nagar, ward-22 Parks 0.03 Work Completed
35 Contruction of Tata Line Garden playing equipments at Shyam Nagar, ward-22 Parks 0.06 Work Completed
36 Contruction of Tata Line Garden civil works at Shyam Nagar, ward-22 Parks 0.2 Work Completed
37 Development of Garden at Ward No. 01 - Khamaria Garden Parks 0.26 Work Completed
38 Development of Garden at Ward No. 16 - Kurud Garden Parks 0.18 Work Completed
39 Development of Garden at Ward No. 60 - Shakti Vihar Garden Parks 0.06 Work Completed
40 Bhilai Water Supply Scheme Phase II - GIS, SCADA, Automation and Metering works Part- 2 Water Supply 0.65 Work Completed
41 DEVELOPMENT OF GARDEN AT WARD NO 03 - MADHU KAMINI GARDEN (Electrification) Parks 0.03 Work Completed
42 DEVELOPMENT OF GARDEN AT WARD NO 03 - MADHU KAMINI GARDEN (Playing Equipment) Parks 0.07 Work Completed
43 DEVELOPMENT OF GARDEN AT WARD NO 07 - MATRI VIHAAR GARDEN (Electrification) Parks 0.03 Work Completed
44 DEVELOPMENT OF GARDEN AT WARD NO 07 - MATRI VIHAAR GARDEN (Playing Equipment) Parks 0.04 Work Completed
45 Bhilai Water Supply Scheme Phase II - Construction of Allied civil works Water Supply 5.09 Work Completed
46 Bhilai Water Supply Scheme Phase II - GIS, SCADA, Automation and Metering works Part -1 Water Supply 8.3 Work Completed
47 Bhilai Water Supply Scheme Phase II - Electro Mechanical works and Augmentation of Sub Statios for Intake Station Water Supply 16.57 Work Completed
48 Bhilai Water Supply Scheme Phase II - Construction of Distribution Part-1 Water Supply 77.04 Work Completed
49 Bhilai Water Supply Scheme Phase II - Construction of OHSR Water Supply 25.65 Work Completed
50 Bhilai Water Supply Scheme Phase II - Construction of Rising Mains Water Supply 37.68 Work Completed
51 DEVELOPMENT OF GARDEN AT WARD NO 03 - MADHU KAMINI GARDEN (Civil Work) Parks 0.35 Work Completed
52 DEVELOPMENT OF GARDEN AT WARD NO 07 - MATRI VIHAAR GARDEN (Civil Work) Parks 0.43 Work Completed