| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Development of Children Park - SAAP 3 (Year 3) | Parks | 0.67 | Work Completed |
| 2 | Development of Children Park - SAAP 3 (Year 2) | Parks | 0.67 | Work Completed |
| 3 | Development of Children Park - SAAP 3 (Year 1) | Parks | 0.66 | Work Completed |
| 4 | Augmentation and Strengthening of Urban Water Supply - SAAP 3 | Water Supply | 126.76 | Contract Awarded |
| 5 | Augmentation and Strengthening of Urban Water Supply - SAAP 2 | Water Supply | 49.45 | Work Completed |
| 6 | Development of Park in Argora | Parks | 2 | Work Completed |
| 7 | Augmentation and Strengthening of Urban Water Supply - SAAP 1 | Water Supply | 89.94 | Contract Awarded |
| 8 | Development of Children Park, Morhabadi | Parks | 1.36 | Work Completed |