1 Strengthening the green spaces and parks in East Delhi-II Parks 2.11 Work Completed
2 Rehabilitation of Yamuna Vihar STPs Sewerage/Septage 60.75 Work Completed
3 Strengthening the green spaces and parks in East Delhi (Ph-III) Parks 3.92 Work Completed
4 Rejuvenation of Shahdara Jheel Water Supply 14.17 Work Completed
5 Faecal Sludge management generated from existing community toilet complexes & MC Pry. School toilets in EDMC areas. Sewerage/Septage 41.49 Work Completed
6 P/L/J water supply distribution network in Shri Ram Colony, Rajiv Nagar under Karawal Ngar (AC-70) Water Supply 3.89 Work Completed
7 P/L/J water supply distribution network in village Sabhapur Extended Abadi under, Karawal Nagar (AC-70) Water Supply 3.56 Work Completed
8 P/L/J water supply distribution network in B to G Block Sonia Vihar Karawal Nagar (AC-70) Water Supply 11.34 Work Completed
9 P/L/J feeder and peripheral water mains in the command of 26.80 ML UGR/BPS, Sonia Vihar (AC-70) Water Supply 36.52 Work Completed
10 Construction of 5.90 MG (26.80 ML) UGR/BPS at Sonia Vihar (AC-70) Water Supply 33 Work Completed
11 Strengthening the green spaces and parks in East Delhi. (Phase-I, total project cost is Rs. 10.00 Crores), to be carried forward to the next Financial Year. Parks 0.52 Work Completed