1 Extension of Distribution System for a Total of 100 Kms in Various Zones Using PVC pipes Including Road Restoration Charges-Phase 1 Water Supply 36.75 Work Completed
2 AWSS to Kollam Corporation -Improvements to Water supply in Vasoorichira zone - Interconnecting 20 LL OHSR with Existing Distribution Network Water Supply 0.5 Work Completed
3 Construction and Renovation of Footpath and Supporting Structures- Phase V- Chinnakkada-Thamarakkulam Area Urban Transport 1.7 Work Completed
4 Construction of drains at various Municipal Locations/roads -phase II Kaikulangara Drainage 0.74 Work Completed
5 Transformer,power line extension Water Supply 2.75 Work Completed
6 Comprehensive WSS to Kollam Municipal Corporation- Construction of 12m dia intake well at Njankadavu Water Supply 2.01 Work Completed
7 Improvement of existing WS System-Supply,errection and commissioning of Chlorinator system to booster pumphouse at Ananathavalleeswaram with 100Kg Chlorine cylinder. Water Supply 0.09 Work Completed
8 Improvement of existing WS System-Supply,errection and commissioning of Chlorinator system to Tubewell pumphouses in Kollam corporation. Water Supply 0.14 Work Completed
9 Improvement of existing WS System-Replacement of 50HP/75HP VT pumpsets at booster pumphouse at Ananathavalleeswaram. Water Supply 0.55 Work Completed
10 Improvement of existing WS System- Division No. 7 to 11 in Kollam Corporation - Replacement of damaged pumpset. Water Supply 0.08 Work Completed
11 Improvement of existing WS System- Division No. 7 to 11 in Kollam Corporation (Laying 110mm PVC 2500m, 90mm PVC 4500m). Water Supply 0.46 Work Completed
12 Improvement of existing WS System-Replacement of contaminated AC pipe lines - from Andamukkam, Thamarakulam, in Kollam Corporation Water Supply 2.73 Work Completed
13 Improvement of existing WS System-Extension of 250mm DI K9 pipe line from Madan Nada Junction to Polyathodu Junction in Kollam Corporation. Water Supply 0.92 Work Completed
14 Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) Water Supply 3.86 Work Completed
15 Development of Existing Parks and Construction of New Parks - Phase I-Kambiyilkkulam (Thrikkadavoor) Parks 0.27 Work Completed
16 Improvement of Parks-phase II -T.M Varghese Park Parks 0.61 Work Completed
17 Construction of FOB at various locations-Phase 2-Chemmanmukku Urban Transport 0.8 Work Completed
18 Construction of FOB at various locations-Phase 1-St.Joseph-Parvathy Mill Jn. Urban Transport 0.93 Work Completed
19 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Kavanad Area Drainage 1.6 Work Completed
20 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Mundakkal Area Drainage 0.2 Work Completed
21 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Vadakkevila-Eravipuram Area Drainage 1.78 Work Completed
22 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Sakthikulangara Area Drainage 0.71 Work Completed
23 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Thangasserry Area Drainage 0.55 Work Completed
24 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Mangad-Arunoottimangalam-Karikkodu Area Drainage 0.15 Work Completed
25 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Kuttichira- Kilikkollur Area Drainage 1.21 Work Completed
26 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase III-Kavanad Area Drainage 1.06 Work Completed
27 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase III-Mundakkal Area Drainage 0.68 Work Completed
28 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase III-SMP Colony-Contonment Drainage 0.7 Work Completed
29 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase II-Sakthikulangara Area Drainage 4.79 Work Completed
30 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase II-Thangasserry Area Drainage 2.64 Work Completed
31 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase II-Mangad-Arunoottimangalam-Karikkodu Area Drainage 2.27 Work Completed
32 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase II-Kuttichira- Kilikkollur Area Drainage 1.07 Work Completed
33 Construction and Renovation of Foot Path and supporting structures - Phase IV Urban Transport 1.71 Work Completed
34 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase IV-Uliakovil Area Phase 3 Drainage 0.15 Work Completed
35 Development of Existing Parks and Construction of New Parks - Phase III -Corporation Park Parks 0.4 Work Completed
36 Development of Existing Parks and Construction of New Parks - Phase II-Veliyilkulangara Parks 0.28 Work Completed
37 Construction and Renovation of Foot Path and supporting structures - Phase III. Urban Transport 2.28 Work Completed
38 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase III-Vadakkevila-Eravipuram Area Drainage 3.34 Work Completed
39 Providing new Water connections with metering system- Phase 2 Water Supply 7.9 Work Completed
40 Development of Existing Parks and Construction of New Parks - Phase I-Asraamom Park Parks 1.07 Work Completed
41 Construction and Renovation of Footpath and Supporting Structures phase II Urban Transport 2.3 Work Completed
42 Stair case in over bridge near Municipal building chinnakkada Urban Transport 0.14 Work Completed
43 Construction of Drains at Various Municipal Corporation Roads/Locations-Phase II-Uliakovil Area Drainage 2.28 Work Completed
44 Sewage Treatment Plant-Zone A1-Phase 2 Sewerage/Septage 6.91 Work Completed
45 Comprehensive WSS to Kollam Municipal Corporation-Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira Water Supply 57.22 Work Completed
46 Providing new Water connections with metering system - Phase 1 Water Supply 9.28 Work Completed
47 Improvement of Parks-phase II -TK Divakaran Park & Nehru Park Parks 0.5 Work Completed
48 Construction of FOB at various locations-Phase 1-High School Jn. Urban Transport 0.74 Work Completed
49 Uliyakovil-Ashtamudi Phase 2 Drainage 2.26 Work Completed
50 Sewage Treatment Plant-Zone A1 Phase 1 Sewerage/Septage 25 Work Completed
51 Rain Water Harvesting-Phase 1 Water Supply 2.22 Work Completed
52 Improvement of existing WS System-Replacement of contaminated AC pipe lines in Kollam Corporation. Water Supply 1.34 Work Completed
53 Improvement of Parks-phase 1(TK Divakaran Park and Nehru Park) Parks 0.28 Work Completed
54 Footpath from AR Camp to Railway Station Road -Phase 1 Urban Transport 0.4 Work Completed
55 Uliyakovil-Ashtamudi Phase 1 Drainage 0.41 Work Completed