| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Sewerage Project Phase-2 under AMRUT(against savings of SAAP I ,II & III) | Sewerage/Septage | 74.29 | Contract Awarded |
| 2 | sikar Green Space Part -3 | Parks | 1.32 | Work Completed |
| 3 | sikar Green Space Part -2 | Parks | 0.5 | Work Completed |
| 4 | sikar Green Space Part -1 | Parks | 0.5 | Work Completed |
| 5 | Water Supply Management | Water Supply | 30.37 | Work Completed |
| 6 | Sewerage and Septage Management under AMRUT Scheme GoI for Sikar Town, Rajasthan | Sewerage/Septage | 109.69 | Work Completed |