| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Development and Rejuvenation of Haibatmau Lake park under green parks and open space component of AMRUT. | Parks | 20.16 | Work Completed |
| 2 | Construction of Central Control Room at Amrut Directorate for real time monitoring of different parameters of tube-wells, OHT being operated by SCADA in different cities of U.P. | Water Supply | 2.68 | Work Completed |
| 3 | Monitoring of quality & quantity of inffluent & effluent of 58 No. STP construted in Uttar Pradesh by SCADA System | Sewerage/Septage | 17.32 | Work Completed |
| 4 | Construction of 120 MLD STP, MPS and other allied works at GH Canal, Lucknow | Sewerage/Septage | 264.46 | Work Completed |
| 5 | Sewer House Connection in Sewer District-1 & other allied works, Lucknow | Sewerage/Septage | 42.37 | Work Completed |
| 6 | Beautification and Development of Park behind Annapurna Complex, Vidyawathi Ward in Green Parks and Spaces head. | Parks | 0.37 | Work Completed |
| 7 | Construction and Beautification of Peace Park, Vijay Khand-2, Gomti Nagar, Lucknow under SAAP 2017-20 under Green Parks and Spaces head. | Parks | 2.16 | Work Completed |
| 8 | Infrastructure development work of under construction Central Control Station at AMRUT Directorate, Lucknow | Water Supply | 3.52 | Work Completed |
| 9 | Lucknow Septage Management(Co- treatment) | Sewerage/Septage | 3.01 | Work Completed |
| 10 | Construction of 1.8 MW Grid connected Solar PV Plant at 3rd Water Works, Kathauta, Lucknow | Water Supply | 17.21 | Work Completed |
| 11 | Vikarmadiyat Marg & Near Area Sewer Laying Works, Lucknow | Sewerage/Septage | 40.19 | Work Completed |
| 12 | Sewer House connection, Sewerage District-4, zone-4, Phase-2 | Sewerage/Septage | 81.32 | Contract Awarded |
| 13 | Sewerage Works for the Smart City, Lucknow ( Sewerage District IV, Zone I, Part II) | Sewerage/Septage | 257.25 | Work Completed |
| 14 | Water Supply Scheme Smart City, Lucknow | Water Supply | 32.69 | Contract Awarded |
| 15 | Construction of 60 MLD Ultra High Rate Clarifier in Aishbagh Water Works in Water Supply District-A, Lucknow | Water Supply | 117.35 | Work Completed |
| 16 | Renovation of Balaganj Water Works in water supply District - A, Lucknow | Water Supply | 3.18 | Work Completed |
| 17 | Construction of Grid Connected Solar Power Plant at 345 MLD STP, Bharwara, Lucknow | Sewerage/Septage | 12.75 | Work Completed |
| 18 | Laying of Sewer line in Dist-4, Zone-4, Lucknow | Sewerage/Septage | 173.21 | Contract Awarded |
| 19 | Labour Colony Sarvodaya Park, Sector 13 | Parks | 0.35 | Work Completed |
| 20 | Sachin Tendulkar Park | Parks | 0.29 | Work Completed |
| 21 | Shachivalay Colony Park | Parks | 0.86 | Work Completed |
| 22 | PK Srivastava Park | Parks | 0.36 | Work Completed |
| 23 | Green Belt Park | Parks | 0.78 | Work Completed |
| 24 | Vishal khand Park | Parks | 0.29 | Work Completed |
| 25 | Napier Park | Parks | 0.52 | Work Completed |
| 26 | Central Park | Parks | 0.48 | Work Completed |
| 27 | Navratan park | Parks | 0.62 | Work Completed |
| 28 | Patel Park | Parks | 0.36 | Work Completed |
| 29 | Abhishekpuram Water supply scheme | Water Supply | 16.83 | Work Completed |
| 30 | Construction of Boundary Wall, CCTV and Watch Tower for protection of 3rd Water Works land, Lucknow city | Water Supply | 13.59 | Work Completed |
| 31 | Construction of Bondary Wall for Land Protection of V Jalkal | Water Supply | 3.49 | Work Completed |
| 32 | House connection for water supply with existing main for district -B,C & D | Water Supply | 37.58 | Work Completed |
| 33 | House connection for water supply with existing main for district -A | Water Supply | 27.81 | Work Completed |
| 34 | Construction of House Connecting Chamber at Sewerage District-III Part-II, Lucknow | Sewerage/Septage | 71.06 | Work Completed |
| 35 | Construction of House Connecting Chamber at Sewerage District-III Part-I, Lucknow | Sewerage/Septage | 130.7 | Work Completed |
| 36 | Rehabilitation of rising Main from CGSPS to Kukrail IPS at Lucknow | Sewerage/Septage | 15.7 | Work Completed |
| 37 | Construction of House Connecting Chamber at Sewerage District I, Lucknow | Sewerage/Septage | 58 | Work Completed |