S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Drainage Scheme Part-3 Drainage 31.67 Work Completed
2 Sewerage Scheme Part-3 Sewerage/Septage 4.34 Work Completed
3 Water Supply Part-3 Water Supply 3.03 Work Completed
4 Green Space & Park Part-3 Parks 0.32 Work Completed
5 Green Space & Park-2 Parks 0.5 Work Completed
6 Drainage Scheme Part-2 Drainage 23 Work Completed
7 Sewerage System Part-2 Sewerage/Septage 2 Work Completed
8 Sewerage Scheme Part-1 Sewerage/Septage 1.5 Work Completed
9 Water Supply Part-2 Water Supply 3.3 Work Completed
10 Water Supply Part-1 Water Supply 8 Work Completed