| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
Milestone |
|---|---|---|---|---|
| 1 | Providing & Laying 300mm to 1000mm nominal Internal Peripheral sewer lines for Jaunapur GOC in Chattarpur AC and Construction of 8.5MGD Sewer Treatment Plant (STP) at Fatehpur Beri along with associated / allied appurtenant work on DBO basis including 15 years O&M. | Sewerage/Septage | 366.25 | Contract Awarded |
| 2 | Providing & Laying 300mm to 900mm nominal Internal Peripheral sewer lines for Tajpur Pahadi GOC in Badarpur AC and constuction of 18.5MGD Sewer Treatment Plant (STP) (Excluding O-Zone) in Badarpur AC and Construction of 18.5MGD Sewage Treatment Plant (STP) at Tajpur Pahadi along with associated/allied appurtenant work on DBO Basis including 15 years O&M | Sewerage/Septage | 235.36 | Contract Awarded |
| 3 | Augmentation/up-gradation of 10MGD STPYamuna VIhar Ph-I | Sewerage/Septage | 127.16 | Contract Awarded |
| 4 | Upgradation and capacity Augmentation of Keshopur STP Phase-I from 12 MGD to 18 MGD along with 12 years comprehensive operation & maintenance | Sewerage/Septage | 167.67 | Contract Awarded |
| 5 | Supply, Insttalation, Testing & Commissioning(SITC) of Sludge management at various STPs in Delhi along with rehabilitation of digestors with 15 years of O&M | Sewerage/Septage | 1721.24 | NIT Issued |
| 6 | Up-gradation and capacity augmentation of existing STPs at vasant Kunj ,Mehruli, Ghitorni and 16 MGD okhla with treated effluent parameter of BOD/TSS as 10/10mg/l with nutrient P<1 and Pathogen<230MPN and Odour Control including operation and maintenance of 11 years | Sewerage/Septage | 356.85 | Contract Awarded |
| 7 | Rehabilitation/up-gradation of existing 25 MGD STP Ph-III Yamuna Vihar from 25 MGD to 40 MGD and construction of new 15 MGD STP Ph-IV at Yamuna Vihar. | Sewerage/Septage | 403.25 | Contract Awarded |
| 8 | Revised -MCD-Development of Urban Green Recreational Space in (a) Park at Mayapuri near DTC Depot & (b) Park near Janakpuri West metro station in West zone. | Parks | 5.250 | Contract Awarded |
| 9 | DJB- Providing & Laying Internal & Peripherial Line in Hasanpur GOC under the command of Proposed STP at Hasanpur. | Sewerage/Septage | 101.24 | Contract Awarded |
| 10 | MCD- Park: Development of Urban Green Recreational Space: (a) Park Swasthaya Vihar near District Centre Laxmi Nagar (b) Park near Pkt A-3, Mayur Vihar Phase–III | Parks | 5.250 | Contract Awarded |
| 11 | MCD- Park: Development of Urban Green Recreational Space in (a) Park at M- block GK-2 (b) Park at near PVR Saket in South zone. | Parks | 5.250 | Contract Awarded |
| 12 | MCD- Park: Development of Urban Green Recreational Space in Ajmal Khan park , Karol Bagh zone | Parks | 3.150 | Contract Awarded |
| 13 | MCD- Installation of STP at outfall drain near Naag Mandir, Sultanpuri, AC-10, Rohini, Delhi. | Sewerage/Septage | 0.97 | Contract Awarded |
| 14 | DJB-Providing House sewer connections (HSC) from DJB manholes upto individual household in the area falling under Ranhola GOC. | Sewerage/Septage | 52.93 | Contract Awarded |
| 15 | DJB-Construction of Chambers and laying UPVC pipes for house sewer connections for Zindpur GOC falling under Zindpur WWTP catchment area in Delhi. | Sewerage/Septage | 53.22 | NIT Issued |
| 16 | DJB-P/L 300 to 900 mm dia nominal dia. Internal and Peripheral Sewer Line in Shri Ram Colony, Rajeev Nagar and Part of Sonia vihar in Karawal Nagar, Delhi. | Sewerage/Septage | 74.4 | Contract Awarded |
| 17 | Construction of 15 MGD Wastewater Treatment Plant at Zindpur, power generation and other associated / allied Appurtenant work with effluent standard of BOD-10mg/l, TSS-10mg/l or better on DBO basis and construction of 22 MGD WWPSs at Zindpur & 9 MGD WWTP at Hiranki including rising mains in Narela AC. | Sewerage/Septage | 233.05 | Contract Awarded |
| 18 | DJB-Providing / Laying / Jointing Peripheral and internal sewer lines in U/A Colonies of Najafgarh AC(35) of Tajpur GOC and adjoining Colonies to be shifted to Mitraon DSTP from Tajpur DSTP. | Sewerage/Septage | 41.32 | Contract Awarded |
| 19 | DJB-Construction of chamber for house sewer connection for Sant Nagar GOC falling under Coronation pillar catchment area in Delhi | Sewerage/Septage | 63.96 | Contract Awarded |
| 20 | DJB-Construction of 4 Nos. of Decentralized Sewage Treatment Plant and Sewage Pumping Station along with other associated / allied appurtenant work under Najafgarh drainage Zone-- | Sewerage/Septage | 250.22 | Contract Awarded |
| 21 | DJB-Construction of 7 Nos. of Decentralized Sewage Treatment Plant and Sewage Pumping Station along with other associated / allied appurtenant work on under Najafgarh drainage | Sewerage/Septage | 321.33 | Contract Awarded |
| 22 | DJB-Construction of 49.5 MLD Wastewater Treatment Plant at Mitraon with other associated / allied appurtenant work. | Sewerage/Septage | 310.87 | Contract Awarded |
| 23 | DJB-Providing house service connections (HSC) to individual households in Kamruddin Nagar GOC | Sewerage/Septage | 21.13 | Contract Awarded |
| 24 | DJB-Providing House Service Connections To Individual Households In Kirari GoC under EE(PR)SR-I | Sewerage/Septage | 76.25 | Contract Awarded |
| 25 | DJB-Providing House Sewer Connection from nearest DJB manholes upto individual household in left out colonies of Gokalpur AC-68. | Sewerage/Septage | 21.87 | Project Completed |
| 26 | MCD- Development of Xeriecape Garden near Desh Bandhu Apartment in W.No-10E, Shah. (South) Zone | Parks | 0.600 | Project Completed |
| 27 | MCD- Development of Green Space & Herbal Park at 1350, LIG House Kondli W.No. 07-E, Shah. (South) Zone | Parks | 0.880 | Project Completed |
| 28 | MCD- Development of Green Space & other infrastructure at Teacher Park, Nimari Colony, Ward No. 74/Keshav Puram Zone | Parks | 0.880 | Project Completed |
| 29 | MCD- Development of Urban Green Recreation Space at Park near Nehru Enclave Metro Station, Kalkaji | Parks | 1.800 | Project Completed |
| 30 | MCD- Development of Urban Green Recreation Space at Park near Gurudwara Trilokpuri road, Block-36, W.No 01E, Shah. (South) Zone | Parks | 1.250 | Contract Awarded |
| 31 | MCD-Remodeling of existing pump house for sludge drain & construction of STP for supplying treated water to various parks in IP Extension & adjoining areas. | Sewerage/Septage | 9.54 | NIT Issued |
| 32 | MCD-Remodelling of existing pump house for sludge drain & construction of STP for supplying treated water to various parks in Shastri Park & adjoining areas. | Sewerage/Septage | 9.80 | NIT Issued |
| 33 | MCD-Remodelling of existing pump house for sludge drain & construction of STP for supplying treated water to various parks in Sunder Nagri & adjoining areas. | Sewerage/Septage | 9.92 | NIT Issued |
| 34 | MCD-Remodeling of existing pump house for sludge drain & construction of STP for supplying treated water to various parks in Laxmi Nagar & adjoining areas. | Sewerage/Septage | 10.09 | NIT Issued |
| 35 | MCD- Remodeling & Construction of sludge drain from APEEJAY school near DDA land to ................. PWD Outfall Drain at Eklavya Marg, KPZ | Sewerage/Septage | 26.60 | Contract Awarded |
| 36 | MCD-Installation of decentralized sewage treatment plant (STP) & development of Topiary Garden at Park/ Seed bed in Mayur Vihar Ph-II, W.N. 11E | Sewerage/Septage | 0.65 | Contract Awarded |
| 37 | MCD-Installation of decentralized sewage treatment plant (STP) at Senior Citizen Park near Law Apartment, Karkardooma Village & its development, WNo 18E, Shah./ South Zone. | Sewerage/Septage | 0.8 | Contract Awarded |
| 38 | MCD-IInstallation of decentralized sewage treatment plant (STP) at Divyang Park, Rathi Mil, Loni Road & its development in W.No.38-E, Shah/North Zone. | Sewerage/Septage | 1.4 | Project Completed |
| 39 | MCD- Remodelling & Construction of sludge drain at Goinka Road and Kali Road in Ward no. 80N/ M-I/City SP Zone | Sewerage/Septage | 1.25 | Project Completed |
| 40 | MCD- Remodelling & Construction of sludge drain in Shahzada Bagh Extension area in ward no. 82-N, Anand Parbat | Sewerage/Septage | 9.50 | DPR Approved |
| 41 | MCD- Remodelling & Construction of sludge drain in C-Block, Sultanpuri, Ward No.45/N in AC-10, Rohini Zone. | Sewerage/Septage | 0.96 | Project Completed |
| 42 | MCD- Remodelling & Construction of sludge drain from H.No.B-4/288 upto Naag Mandir in Ward No.47/N, Sultanpuri, AC-10-Rohini. | Sewerage/Septage | 0.44 | Project Completed |
| 43 | MCD- Rejuvenation of Lake at Roshanara Bagh, Ward No.78, Kheshav Puram Zone. | WB Rejuvenation | 10.98 | Project Completed |
| 44 | MCD- Remodelling & Construction of sludge drain from Vasundhara Enclave to New Ashok Nagar, Metro Station in New Ashok Nagar Ward No. E-04 in AC-55 | Sewerage/Septage | 20.50 | Contract Awarded |
| 45 | MCD- Remodelling & Construction of sludge drain along Railway Line from Police Chowki to underpass Sawan Park for nearby area Sawan Park, Sawan Park Extension | Sewerage/Septage | 1.49 | Project Completed |
| 46 | MCD- Khasra No. 155 behind Pkt. 1 Sec-7 Dwarka (Palam) in ward No. 54-S, Najafgarh Zone. | WB Rejuvenation | 1.2 | Project Completed |
| 47 | MCD- Behind DTC Terminal in Ward No. 43-S Najafgarh Zone | WB Rejuvenation | 0.75 | Project Completed |
| 48 | MCD- Roshanapura near Senior Secondary School Dharampura in ward No. 44-S, Najafgarh Zone | WB Rejuvenation | 0.75 | Contract Awarded |
| 49 | MCD- C BLOCK, SECTOR-8 Dwarka | WB Rejuvenation | 0.20 | Project Completed |
| 50 | MCD- Village Pochan Pur Sector-23 Dwarka in ward No. 38-S, Najafgarh Zone. | WB Rejuvenation | 0.75 | Project Completed |
| 51 | MCD- Harijan Basti near Ramphal Chowk Sec-7 Dwarka in ward No. 54-S, Najafgarh Zone. | WB Rejuvenation | 1.2 | Project Completed |
| 52 | MCD- Masoodpur Village Park, (Vasant Kunj) in ward No. 69-S, South Zone. | WB Rejuvenation | 0.25 | Project Completed |
| 53 | MCD- Aya Nagar Johad (near Bus Stand ), | WB Rejuvenation | 2.0 | Project Completed |
| 54 | MCD- Primary School Jaunapur,South Zone in ward No. 73-S, South Zone. | WB Rejuvenation | 0.25 | Project Completed |
| 55 | MCD- Khasra No. 155 behind Pkt. 1 Sec-7 Dwarka (Palam) in ward No. 54-S, Najafgarh Zone. | WB Rejuvenation | 1.25 | Project Completed |
| 56 | MCD- Village- Amberhat, Sectior-19, Dwarka, Najafgarh Zone | WB Rejuvenation | 1.25 | Project Completed |
| 57 | MCD- Ghazipur Village behind Subzi Mandi | WB Rejuvenation | 1.2 | Project Completed |
| 58 | MCD- Tahir Pur Village | WB Rejuvenation | 1.3 | Contract Awarded |
| 59 | MCD- Khasra No. 61/26, ( 7-11) Narela, Mata Mansa Devi Mandir | WB Rejuvenation | 1.5 | Project Completed |
| 60 | MCD- Khasra No.396, Pana Paposian, Narela | WB Rejuvenation | 1.5 | Project Completed |
| 61 | MCD (WR)- Naini Lake, Model Town, Keshav Puram, Ward no. 77-N | WB Rejuvenation | 10.7 | Contract Awarded |
| 62 | MCD (WR)- Jahaz Wala Park in Bagdola Village, Sector-8, Dwarka in ward no. 47-S, Najafgarh Zone | WB Rejuvenation | 0.83 | Project Completed |
| 63 | MCD (WR)- Water Body at Bagdola near Malaria Office, Sector-8, Dwarka in ward No. 47-S, Najafgarh Zone | WB Rejuvenation | 0.66 | Project Completed |
| 64 | MCD (WR)- Ghazipur Village near Highway Apartment, Shahdara South Zone ward no. 19-E | WB Rejuvenation | 0.123 | Project Completed |
| 65 | DJB-Providing House sewer connections (HSC) from nearest DJB manholes to individual house in U/A colonies under Vikaspuri GOC | Sewerage/Septage | 28.26 | Contract Awarded |
| 66 | Laying of Sewerage Network in Zindpur GOC | Sewerage/Septage | 341.25 | Contract Awarded |
| 67 | Remodeling and Construction of sludge drain from Rajasthani Pahari on shiv Mandir Road to Mehrauli Badarpur road via Shooting Range road in ward no 169, 170 old 83-S Sangam Vihar, Central Zone. | Sewerage/Septage | 12.3 | NIT Issued |
| 68 | DJB-Providing chamber for House sewer connections for Swaroop Nagar GOC falling under Coronation Pillar catchment area in Delhi | Sewerage/Septage | 27.97 | Contract Awarded |