| S.No. | Project Title | Project Type | Project Cost (in ₹ Cr.) |
|---|---|---|---|
| 1 | Sewerage system for Zone A | Sewerage/Septage | 143.16 |
| 2 | AMRUT 2.0 - Augmentation of 174MLD to 210 MLD of Peruvannamoozhi plant - Replacing of Premo and AC pipe transmission main at Malaparamba and Tali and providing balance FHTCs at kozhikode corporation. | Water Supply | 113 |
| 3 | Renovation of the Kozhikode Corporation Lion's park | Parks | 2.600 |
| 4 | Sewerage System to Kozhikode Corporation -Zone B1- Part1 | Sewerage/Septage | 179.29 |
| 5 | Creating a new pond in Lion's park Kozhikode beach and beautification of its premises | WB Rejuvenation | 5.28 |
| 6 | Rejuvenation of Valiya Parambu kulam | WB Rejuvenation | 0.253 |
| 7 | Rejuvenation of Areekkulam | WB Rejuvenation | 0.275 |
| 8 | Rejuvenation Neelichira | WB Rejuvenation | 0.132 |
| 9 | Rejuvenation of Mundakan Kulam three | WB Rejuvenation | 0.33 |
| 10 | Rejuvenation of Mundakan Kulam one | WB Rejuvenation | 1.1 |
| 11 | Rejuvenation of Pavangad Thamarakulam | WB Rejuvenation | 0.143 |
| 12 | Rejuvenation of Elathur Panchayath Kulam | WB Rejuvenation | 0.1925 |
| 13 | Priority 3 - 24X7 Water supply scheme at Edakkadu and adjacent places | Water Supply | 4.58 |
| 14 | Priority 2 - 24X7 Water supply scheme at Nellikode and adjacent places | Water Supply | 4.19 |