List of Approved Projects
S.No. Project Title Project Type Project Cost
(in ₹ Cr.)
Milestone
1 Development of park near OHT at Gangadharapura Parks 0.440 Contract Awarded
2 Rejuvenation of Muttur Lake in CMC Doddaballapura WB Rejuvenation 4.8 DPR Approved
3 Rejuvenation of Kalyani near Ramanna Bavi Temple at CMC Doddaballapura WB Rejuvenation 0.64 NIT Issued
4 Rejuvenation of Kalyani opposite to court at CMC Doddaballapura WB Rejuvenation 0.483 NIT Issued
5 Rejuvenation of Kalyani near Someshwara temple at CMC Doddaballapura WB Rejuvenation 2.474 DPR Approved
6 Development of park in Karenahalli CMC Doddaballapur Parks 0.440 NIT Issued
7 Development of park in Rajeev Gandhi Ashrya Layout CMC Doddaballapur Parks 0.440 NIT Issued
8 Development of park at Bhuvaneshwari Nagara layout CMC Doddaballapura Parks 0.440 NIT Issued
9 Development of park beside CMC office (M.T. srikantaiah park) Parks 0.440 NIT Issued
10 Providing distribution system with HSCs to Doddaballapur Water Supply 9.55 Contract Awarded